The Far Eastern Design Center is correcting the design documentation for the construction of a site for a border crossing on Bolshoy Ussuriysky Island.

Currently, work on the construction of a site for a border crossing on Bolshoy Ussuriysky Island is underway at sites 7 and 8. The foundation is being poured and the site is collapsing. Next, the soil and vegetation will be removed, and the site will be filled in to the design marks. After leveling the site, a layer of geotextile is laid. Then - filling of the working layer.
- Now the work is ahead of schedule. This requires the use of more equipment. This means that technical design solutions are also changing: work schedules, the number of special vehicles, and the location of the construction site are changing," said Nikita Bozhok, General Director of the Far Eastern Design Center.
Work is also underway to establish a new river quarry near the construction site. Thanks to this, it will be possible to reduce the delivery shoulder by 4 times, which means that the work period will also be shortened.
The Far Eastern Design Center will support the project until its complete completion.